Summary: "At the March 8, 2025 City Council Meeting, members of the City Council approved a professional services agreement for water and street infrastructure improvements on Squaw Road and adjoining side streets. A kickoff meeting was held March 20, 2025, with the city staff and Jacob Martin, LLC, to discuss the project. Design is officially underway on the following items: • Street Reconstruction • Water Distribution System Requirements • Drainage improvements."

• Latest Update: 02 May, 2025


• Note: Willow Park Civics is about Willow Park but is NOT associated with or managed by the City of Willow Park.









City of Willow Park. Squaw Creek Road Project, About The Project

Squaw Creek Road Project, About The Project, City of Willow Park, 23 April 2025


"At the March 8, 2025 City Council Meeting [1], members of the City Council approved a professional services agreement for water and street infrastructure improvements on Squaw Road and adjoining side streets. A kickoff meeting was held March 20, 2025, with the city staff and Jacob Martin, LLC, to discuss the project. Design is officially underway on the following items:


• Water Distribution System Requirements:

• Water Line Replacement: approximately 7,950 feet of eight-inch line along Squaw Creek Road

• Water Line Replacement: approximately 6,180 feet of eight-inch line along Yucca, Mesa, Cactus, and Verde Roads


Street Reconstruction:

• Squaw Creek Road Reconstruction: Ranch House Road to Sam Bass Road (7,950 feet)

• Yucca Road Reconstruction: Verde Road to Squaw Creek Road (1,775 feet)

• Mesa Road Reconstruction: Verde Road to Squaw Creek Road (1,450 feet)

• Cactus Road Reconstruction: Verde Road to Squaw Creek Road (1,100 feet)

• Cactus Court Reconstruction: Cactus Road to end of cul-de-sac (250 feet)

• Verde Road Reconstruction: HOA Entrance to Yucca Road (1,605 feet)


• Drainage improvements:

• Ditch and culvert improvement along and crossing Squaw Creek Road

• Drainage improvements along and crossing Yucca, Mesa, Cactus, and Verde Roads


These activities will be funded equally through fund balance from the General Fund, Water Fund, and Drainage Fund.


Cost of engineering by Jacob Martin, LLC,: $525,000 (estimate may vary depending on scope of design and construction surveying)"





Willow Park Sources and Resources

[1] 08 April 2025 Council Meeting, Willow Park Civics Blog, posted 04 April 2025






Comments


Commenting on this post isn't available anymore. Contact the site owner for more info.
bottom of page